Building Codes Department Commercial/Industrial Submittal Requirements
Adopted Code:
- 2009 Edition as Amended
- International Building Code
- International Residential Code
- International Mechanical Code
- International Fuel Gas Code
- International Fire Code
- International Plumbing Code
- International Property
- Maintenance Code
- National Electrical Code 2008 Edition
Design Criteria:
- Wind, 90mph Exposure C @ 3 second gust
- Seismic, Zone 2A
- Snow, 20 PSF
- Roof Classification, Min. Class C Fire Rated
- Flood Plain Info, Base Flood Elevation
Design Submittal:
- Professional Stamp: Each set signed and dated.
- Architect/Engineer must certify that plans meet design criteria.
- Two sets of construction plans for review per building.
- 3 Site Plans
- Special Inspections May Be Required For Concrete, Masonry, Soils, etc.
- Complete list of contractors and subcontractors. All contractors and subcontractors shall be licensed with the City of Bonner Springs.
- Rapid Key Entry System (Knox Box) is required on all commercial and industrial occupancies.
- This department will provide a stamped approved set of plans to be kept on job site.
Note: Plans submitted to the Planning Department are not forwarded to the Building Department – A separate submittal is required..
Permit Processing Goals:
The Codes Department will try to meet the following timetable:
- Review Commercial or Industrial Set of Plans within 7-10 days.
- A permit cannot be issued until the Governing Body has approved all Planning documents and Public Improvements for Commercial or Industrial projects.
|